Independent comparisons. We may earn from shop links. More info

Underground drainage pipe fall: 1:40 in millimetres

RulesOctober 20267 min read
Black underground drainage pipe laid to a measured fall in a garden trench

A low-flow 100 mm foul drain needs an underground drainage pipe fall of 1:40, or 25 mm per metre. A one-metre shop pipe does not set that gradient for you.

Top pick: GIONAR catch-basin and downspout kit
Top pick: GIONAR catch-basin and downspout kit
See comparison →

You have a short run of foul drain to lay from a gully across the garden, the 110 mm pipe is still in its wrap, and the trench bed looks almost level. Level is the failure. Too flat a 100 mm pipe holds solids, and the underground drainage pipe fall is a measured drop along the trench, not a feature printed on a one-metre length from amazon.co.uk.

The figures below are the LABC reading of Approved Document H for England and Wales. Scotland and Northern Ireland have their own technical handbooks. Nothing here designs a connection to a public sewer.

In short

A 100 mm foul drain carrying under 1 litre a second wants a fall of 1:40, which is 25 mm per metre. Where the flow is over 1 litre a second and a WC is connected, LABC allows 1:80, or 12.5 mm per metre. A short plastic length from a shop does not create either gradient, so you set the drop in the trench bed.

What underground drainage pipe fall a foul pipe needs

Foul water has to keep moving. LABC, writing up Approved Document H, says an underground foul drain is at least 75 mm, and 100 mm if it serves a WC. Under 1 litre a second, that 100 mm pipe wants 1:40. Over 1 litre a second, and with a WC connected, LABC allows 1:80, while a 150 mm drain can be 1:150. Keep those as the LABC reading.

Council pages often compress the table. Redbridge states 1:80 where a WC is on a 100/110 mm pipe, and 1:150 on 150/160 mm where there are enough WCs, and that version drops the low-flow 1:40 case. If the summaries disagree, follow the Approved Document and use LABC's flow split. If you do not know whether the run is under or over 1 litre a second, keep the steeper figure, because a small flow leaves solids on a flat invert. Several WCs can be the higher-flow case, and that judgement is design work.

Set pegs at each end, pull a string line, and measure the drop with a tape before any pipe touches the bed. Backfilling first locks a flat bed in place. These millimetres are the England and Wales route, including the Welsh Government copy of the same document. They are not the Scottish or Northern Ireland handbook.

What 1:40 and 1:80 mean in millimetres

1:40 is one unit down for every 40 along. A metre is 1,000 mm, so the fall is 25 mm per metre, and 1:80 is 12.5 mm per metre. Four metres at 1:40 drops 100 mm, and six metres drops 150 mm. The same six metres at 1:80 drops only 75 mm, which a sagging string will hide. A one-metre offcut falling 25 mm along its own body says nothing about the rest of the lawn.

A 600 mm spirit level can check the ratio on a straight bed. At 1:40 the downhill end wants a 15 mm packer, because 600 divided by 40 is 15, and at 1:80 the packer is 7.5 mm. Check two or three positions rather than one reading at the gully. If you are 10 mm short at the end of a four-metre run, the pipe will not invent that drop after you joint it. Using 12.5 mm per metre on a low-flow 100 mm pipe is the flat drain LABC is trying to stop.

Pipe size before you pick a gradient

Gradient comes after diameter. LABC's minimum for underground foul drainage is 75 mm, and the pipe becomes 100 mm as soon as a WC connects, so a run that might gain a loo is already a 100 mm job. Buying 75 mm today forces a second trench later. The 1:150 figure belongs to 150 mm pipe, about 6.7 mm per metre, and it is not a substitute on a 100 mm pipe. Shops often print 110 mm on the pipe the guidance calls 100 mm, which Redbridge pairs as 100/110 mm.

Solvent-weld waste and ring-seal underground pipe can share a headline size and still be different systems. The PVC pipe comparison is about waste joints, not a buried foul run with a rodding point. On amazon.co.uk the eco-filtration listing is a 1 m black solvent-weld waste pipe at a stated 110 mm and £19.99, with no ring seal and no British Standard named. A stored size of 11 cm by 10.2 cm does not describe that metre. Five short UK reviews, inside a 4.2 from 17, never show a trench.

The GIONAR catch-basin kit, the highest score in the set, is £20.99 and includes a basin, a pipe stated from 16.14 inches to 5.1 feet, a hose adapter, and a grate. The amazon.co.uk line is 4.4 from 134 ratings for short rainwater runs. There is no 110 mm socket, and a stored 41 cm outside diameter conflicts with a 6.5 cm width. A qualifying purchase through our links can earn a commission at no extra cost to you. Neither box sets the fall, so the gaps stay on the underground drainage pipe page.

Why a long plastic pipe ends up with a backfall

A fall on the pegs can disappear once the pipe is in. LABC points out that long plastic pipes can bow and create a backfall, a short length that slopes the wrong way so solids sit in the hollow. At 1:80 you have 12.5 mm of drop per metre, so a pipe on a socket at each end that sags 20 mm in the middle has already built a sump. The upstream face falls in and the downstream face rises. Packing soil only under the collars, where the pipe looks supported, is the usual way that hollow appears.

Plastic moves a little once the trench is warm and the backfill is on it, so a fair line at noon can hold water by the weekend. You meet it as a slow gully or a rod that stops in the same place, and rodding clears the wad without adding the missing fall. Lay the pipe on a continuous bed, and check the invert at the sockets and halfway between them before you cover the crown. Lower a high joint by easing the bed. Forcing the barrel down with a boot starts the next kink.

LABC names the bow. The note we used does not give a trench width, a gravel grade, or a clip spacing, and this article will not invent them. A rigid solvent-weld waste pipe is a poor stand-in even when the diameter looks right, because underground plastic is specified around flexible joints.

Where a garden drain stops being a DIY job

You can measure 25 mm per metre and still be outside the job a shopper should finish alone. Approved Document H covers underground foul drainage from the building to the sewer, and it expects a connection to a public sewer where that is practicable. Opening the sewer and agreeing the invert are not a weekend with a 1 m offcut. This page cannot tell you that your gully is notifiable. Building control applies the document in England and Wales, while Scotland and Northern Ireland use their own technical handbooks.

If the public sewer sits higher than the garden outlet, no underground drainage pipe fall in the lawn will lift the sewage. Extra steepness only uses depth you may not have. Put a tape on both inverts, and if the sewer end is the high end, backfill and get someone who designs drains. A pump or a new route is that design, and it is not inside a catch-basin kit whose pipe stops at 5.1 feet. The one-metre solvent-weld pipe at £19.99 has the same limit: it does not keep a foul run self-cleansing.

We checked the LABC article, the 2015 Approved Document H, the Welsh Government copy of that guidance, the Redbridge summary, and the amazon.co.uk listings above, in October 2026. Redbridge stays secondary to the Approved Document. We did not dig a test trench or reproduce British Standard text.

Common questions

What fall does a 100 mm foul pipe need?
LABC's reading of Approved Document H puts a 100 mm foul drain at 1:40 when the flow is under 1 litre a second. That is 25 mm of drop per metre. Where the flow is over 1 litre a second and a WC is connected, LABC allows 1:80, which is 12.5 mm per metre. A council page that only quotes 1:80 has compressed the table. Follow the Approved Document, and use the LABC flow split if the summaries differ. These figures are the England and Wales route.
What is 1:40 in millimetres per metre?
1:40 means one unit of drop for every 40 units of length, so 25 mm per metre. A 4 metre run drops 100 mm. A 6 metre run drops 150 mm. On a 600 mm straightedge the same ratio is 15 mm of packer under the downhill end. 1:80 is half that steepness, 12.5 mm per metre, and a soft bed can swallow it. Mark the pegs and check the drop before the pipe goes in.
Is rainwater the same fall as a foul drain?
No figure in this article is a rainwater gradient. Foul water and rainwater are different drains, and a blog that puts both falls in one sentence is guessing. A catch-basin kit that moves water off a downpipe is a rainwater product. It does not become a foul drain because you bury the hose. Keep the two systems apart, and do not copy 1:40 or 1:80 onto a gutter run from this page.
Can I use 75 mm if there is no WC?
LABC states a minimum of 75 mm for an underground foul drain, and 100 mm where the drain serves a WC. A 75 mm pipe is the wrong size the day a WC is added. Listings that say 110 mm are the size UK buyers meet for that 100 mm underground pipe, which Redbridge pairs as 100/110 mm. A 150 mm drain is a different case and can be as flat as 1:150. Do not use that flatter number on a 100 mm garden pipe.
Why do long plastic pipes end up with a backfall?
LABC warns that long plastic pipes can bow and create a backfall, a short stretch that slopes the wrong way. The bow only has to exceed the fall in that bay. At 1:80 that fall is 12.5 mm per metre, so a sag between two high spots is enough to hold solids. Support the pipe on a continuous bed rather than on mounds at the sockets. This page does not set a bedding depth or a clip spacing.
Do I need building control for a new drain?
This article does not tell you whether your garden job is notifiable. In England and Wales, underground foul drainage from the building toward the sewer is the subject of Approved Document H, and building control is the office that applies it. Scotland and Northern Ireland use their own technical handbooks, so the millimetre figures here are not their text. Ask the council before you dig a new connection. A shop listing cannot answer that question for you.
What if the public sewer is higher than my garden?
A fall only runs downhill. If the public sewer invert sits above your outlet, a steeper gradient in the lawn cannot climb that difference. Approved Document H expects a connection to a public sewer where practicable, and this article does not design that connection, a pump, or a new route. Stop when the levels do not work on a tape. That is work for building control and someone competent to design the drain.
Is a 1 m offcut from a shop the right product?
A one-metre length does not hold the fall of a longer drain. The gradient lives in the trench. On amazon.co.uk, the eco-filtration listing is a 1 m black solvent-weld waste pipe at a stated 110 mm, priced at £19.99, with no ring seal and no British Standard named. The GIONAR catch-basin kit at £20.99 reaches a stated 5.1 feet and is rainwater only. Compare those limits on the underground drainage pipe page before you treat either box as a foul run.
Peter F.
DIY & tools

Peter F. is the editor for DIY & tools at productscompared.co.uk. Comparisons in this category are checked against amazon.co.uk listings, review evidence and public UK sources.

Updated: October 2026

Related articles